BREEAM Offices 2006

http://www.breeam.org/filelibrary/14__DP_Pre-assessment_Estimator_2006_-_Final.pdf

DESIGN & PROCUREMENT
PRE-ASSESSMENT ESTIMATOR

The pre-assessment estimator allows a quick evaluation of the likely rating to be achieved under a formal BREEAM Offices 2006 assessment (effective from 1st March 2006). The checklist is a simplified version of the full method, for this reason the final rating may vary.

Section: Water
Page: 9 of 16
Credit reference: W03
Points: 0.83
Description: Where evidence is provided that a leak detection system is specified or installed

Section: Pollution
Page: 14 of 16
Credit reference: P02
Points: 1 for each description
Description: Where evidence provided demonstrates that refrigerant leaks can be detected or where there are no refrigerants specified for use in the building or development.

Where there are refrigerants, evidence should be provided to demonstrate that the provision of automatic refrigerant pump down is made to a heat exchanger (or dedicated storage tanks) with isolation valves.

NOTE: These point scores ARE cumulative.



Management & Operation Pre-Assessment
Estimator Criteria

http://www.breeam.org/filelibrary/14__MO_Pre-assessment_Estimator_2006v1_1.pdf

Section: Water
Page: 9 of 16
Credit reference: W03
Points: 0.56
Description: Where evidence is provided that a leak detection system is specified or installed

Section: Pollution
Page: 14 of 16
Credit reference: P02
Points: 1.36 for each description
Description: Where evidence provided demonstrates that refrigerant leaks can be detected or where there are no refrigerants specified for use in the building or development.

Where there are refrigerants, evidence should be provided to demonstrate that the provision of automatic refrigerant pump down is made to a heat exchanger (or dedicated storage tanks) with isolation valves.



BREEAM Industrial 2006

http://www.breeam.org/filelibrary/14__IND_PreAssessmentEstimator__fitted_out_REV01.pdf

BREEAM Industrial 2006
PRE-ASSESSMENT ESTIMATOR
Fitted Out Buildings

Section: Water
Page: 9 of 16
Credit reference: W03
Points: 1 with Offices, 1 without offices
Description: Where evidence is provided that a leak detection system is specified or installed

Section: Pollution
Page: 14 of 16
Credit reference: P02
Points: 1.15 with Offices, 1.25 without offices
Description: Where evidence provided demonstrates that refrigerant leaks can be detected AND that the provision of automatic refrigerant pump down is made to a heat exchanger (or dedicated storage tanks) with isolation valves OR where there are no refrigerants specified for the development.



http://www.breeam.org/filelibrary/14__IND_PreAssessmentEstimator_speculative_REV01.pdf

BREEAM Industrial 2006
PRE-ASSESSMENT ESTIMATOR
Speculative Buildings

Section: Water
Page: 9 of 16
Credit reference: W03
Points: 1 with Offices, 1 without offices
Description: Where evidence is provided that a leak detection system is specified or installed

Section: Pollution
Page: 14 of 16
Credit reference: P02
Points: 1.15 with Offices, 1.36 without offices
Description: Where evidence provided demonstrates that refrigerant leaks can be detected AND that the provision of automatic refrigerant pump down is made to a heat exchanger (or dedicated storage tanks) with isolation valves OR where there are no refrigerants specified for the development.



 
 